Name of the task : Fabrication and delivery of the steel structure of roller table by the unloading side of the Sump Furnace on the premises of the Huta Bankowa in Dąbrowa Górnicza.

Industry: structural, anti-corrosion.

Scope of performed works:

  • Disassembly of old roller table
  • Delivery of new elements:
  • Prefabrication and delivery of roller table frame - 45 000 kg,
  • Prefabrication and delivery of platform plates – 3000 kg,
  • Delivery of levelling washers for new equipment - 300 kg,
  • Corrosion protection for new components
  • Assembly of new equipment :
  • Roller table frames on steel washers – 45 000 kg,
  • Drives, gearboxes and other components of the roller table - 50 016 kg,
  • Floor plates along the roller table self-tacking side to secure the transport of the string – 3000 kg

Implementation: 2017-2018

General Contractor / Purchaser: Optimal Sp. z o.o.

Investor: ArcelorMittal Poland S.A.

Subcontractor: HPR Dąbrowa Górnicza S.A.