Name of the task:

Overhaul and modernisation services of production lines in the plants:

  • Blast furnace
  • Steel and semi-finished products,
  • Hot rolling mills

in ArcelorMittal Poland S.A. in Dąbrowa Górnicza.

Industry: mechanical, installation.          

Scope of performed works:

  • Gas installations DN50 ÷ DN400 (gas installation pressure parameters from 4 to 10 bar),
  • Combustion air installations,
  • Evaporator cooling installations,
  • Industrial water installations,
  • Steam installations.

Implementation: 2016

Purchaser: ArcelorMittal Poland S.A.

Investor: ArcelorMittal Poland S.A.

General Contractor: HPR Dąbrowa Górnicza S.A.