Construction of the safety system for the Long Rail Production Line in AMP in Dąbrowa Górnicza
17 April 2020
Overhaul works of equipment and facilities in AMP in Dąbrowa Górnicza
15 April 2020

Work in Eisenhüttenstadt in Germany

Name of the task: Mechanical work and installation of insulation (including prefabrication of sheets, welded mesh and accessories) at the Eisenhüttenstadt plant in Germany

Industry: assembly, insulation, anticorrosion

Scope of performed work:

  • Assemblies,
  • Disassemblies,
  • Isolation,
  • Anticorrosion,
  • Fireproof lining,
  • Deliveries:
  • unloading, storing and handling,
  • weld control with ND test and certification,
  • pressure tests and flushing,
  • control of the fan coupling alignment of the jet cooler,
  • lubrication control of bearings (fans and rollers),
  • help with cold and hot commissioning.

Implementation: 2014-2015

General Contractor / Purchaser: Danieli Centro Combustion SpA

Investor: ArcelorMittal Eisenhüttenstadt GMBH

Subcontractor: HPR Dąbrowa Górnicza S.A.