Name of the task: Reconstruction of the roof of the social and office building in CTL Maczki-Bór S.A.

Industry: construction

Scope of performed work:

  • Dismantling of existing multilayer covering,
  • Renovation of reinforced concrete tides of the roof,
  • Construction of attic walls,
  • Execution of a new insulating and topcoat covering,
  • Execution of roof drains for internal roof drainage,
  • Execution of flashings,
  • Renovation of ventilation chimneys,
  • Blinding the existing chimney hole and construction of a new one,
  • Construction and assembly of lightning protection system on the walls,
  • Warming up the building, silicone plaster, painting with silicone paints,
  • Assembly of entrance ladders on the roof of the building,
  • Assembly of security barriers on the windows,
  • Dismantling sheet metal covers including brackets,
  • Air-conditioning duct passages,
  • Casing on the insulated part of the newly built attic,
  • Disposal of existing downpipe,
  • Renovation of damaged market,
  • Replacing windows,
  • Assembly of the door to the exchanger room.

Implementation: 2010

Purchaser: CTL Maczki-Bór S.A.

Investor: CTL Maczki-Bór S.A.

General Contractor: HPR Dąbrowa Górnicza S.A.