Name of the task: Prefabrication, assembly, testing and commissioning of the flue gas supply system to the air and flue gas ducts of coking battery no. 3, chambers 351 and 352 at JSW KOKS S.A. Przyjaźń Coking Plant in Dąbrowa Górnicza

Industry: structural-mechanical, energy

Scope of performed work:

  • delivery and assembly of:
  • pipes,
  • fittings,
  • steel structure for pipeline supports.

Implementation: 2014

General Contractor / Purchaser: “Chemokor” Sp. z o.o.

Investor: JSW KOKS S.A. Koksownia Przyjaźń Sp. z o.o.