Name of the task: Execution of earthworks, foundation works and structural works for the investment task entitled: “Expansion of the Heavy Dump Oven Installation” in Bolesław Recykling Sp. z o.o.

Industry: construction, structural and assembly, anticorrosion, installation

The works were carried out for the following facilities:

  • Batch breakdowns, including hose transport and storage equipment,
  • Dust extraction cooling systems with pulsed bag filters,
  • Pneumatic transport installations

Implementation: 2011-2012

General Contractor / Purchaser: AMK Kraków S.A.

Investor: Bolesław Recykling Sp. z o.o.