Name of the task: Construction on II stage of flue gas desulphurization installation for WP-70 boiler house in Przedsiębiorstwo Energetyki Cieplnej Sp. z o.o. in Gliwice.

Industry: construction, insulation, structural, installation, anticorrosion.

Scope of performed works:

  • Construction of foundations of oil pumping station tanks, flyovers,
  • Prefabrication of steel structures with corrosion protection,
  • Prefabrication, delivery and installation of gas and flue gas pipes and support structures for pipes,
  • Prefabrication, delivery and assembly of tanks: absorber V=1 360 m3, desulphurization product V=427 m3, lime milk V=146 m3,
  • Thermal insulation of flue ducts, absorber,
  • Ventilation systems, sewage systems,
  • Execution of oil-resistant floors,
  • Assembly of equipment, e.g.: hoists, increment breakers, vibration isolators, fans, etc.,
  • Prefabrication, anti-corrosion protection, delivery and assembly of flue gas desulphurization product tank,
  • Prefabrication, delivery and assembly of the steel structure of the lift shaft.

Implementation: 2015-2017

General Contractor / Purchaser:  Przedsiębiorstwo Energetyki Cieplnej Sp. z o.o. in Gliwice / AMK Kraków S.A.

Investor:  Przedsiębiorstwo Energetyki Cieplnej Sp. z o.o. in Gliwice

Subcontractor: HPR Dąbrowa Górnicza S.A.