Name of the task: Construction of Power Blocks No. 5 and 6 in PGE GiEK SA in Opole Power Plant.

Industry: design, construction, installation.

Scope of performed works:

  • Comprehensive design and assembly work in the field of oil management, including:
  • unloading front (truck and railway) together with registration of NO devices in Transport Technical Inspection,
  • The pumping station together with technological equipment and legalization of the flow measurement system in the Notified Unit,
  • two storage tanks with a nominal capacity of 1 000 m3 each, together with approval and registration in the Office of Technical Inspection and legalization in the Main Office of Measures as measuring vessels for excise settlements,
  • Inter-pipeline installations (unloading and transfer).

Implementation: 2015-2018

General Contractor / Purchaser: Mostostal Power Development Sp. z o.o.

Investor: PGE Polska Grupa Energetyczna S.A.

Subcontractor: HPR Dąbrowa Górnicza S.A.