Name of the task: Construction of a new Batch plant with the requirements of the Flint Glass Production Furnace in Stolzle Glassworks in Częstochowa.
Industry: construction, installation
Scope of performed work:
- Supply of mechanical and pneumatic transport equipment of the Batch Plant and Bath Hall,
- Comprehensive assembly of the process line of the Batch Plant and Bath Hall:
- conveyors: belt, bucket and scraper conveyors,
- hammer crusher BRV 70,
- two-way distributors,
- magnetic separators and metal detector,
- pneumatic transport installations (with wear-resistant lining),
- compressed air systems,
- Cold commissioning and technological commissioning (hot commissioning).
Implementation: 2010-2011
General Contractor / Purchaser: Zakład Automatyki ZREMB Warszawa Sp. z o.o.
Investor: STOLZLE Glassworks in Częstochowa
Subcontractor: HPR Dąbrowa Górnicza S.A.